The highly anticipated, Elizabeth Line is set to open this week, marking the historic end of the Crossrail project.
Over its 20 years' progress, the project suffered numerous setbacks, delays and budget cuts.
But now its finally completely and will officially be open on May 24 in perfect time to mark the Queen's Platinum Jubilee.
But before it opens, we thought we'd look back on the last 20 years and look at the project's timeline.
Crossrail's Elizabeth line full timeline:
– January 2002: Cross London Rail Links Ltd, a joint venture with the Strategic Rail Authority and Transport for London (TfL), is set up to develop plans for Crossrail.
– July 2004: The Government commits to introducing legislation to enable Crossrail to proceed.
– October 2007: Prime Minister Gordon Brown gives the green light for the project. It is expected to cost £15.9 billion and open in December 2017.
– May 2009: London Mayor Boris Johnson and Transport Secretary Lord Adonis break ground on the project at Canary Wharf.
– October 2010: Crossrail’s budget is cut to £14.8 billion in the Conservative and Liberal Democrat coalition government’s comprehensive spending review. Its opening date is pushed back 12 months to December 2018.
– January 2014: The National Audit Office says the scheme is “just behind schedule”, adding that Crossrail Ltd “remains confident” it will open on time.
– May 2015: Tunnel boring is completed as a tunnelling machine named Victoria arrives at Farringdon. Some 13 miles of new tunnels have been dug under London.
– February 2016: The Queen visits Bond Street station and announces the railway will be named the Elizabeth line in her honour.
– July 2018: Rail minister Jo Johnson announces that Crossrail’s budget has risen to £15.4 billion as “cost pressures have increased across the project”.
– August 2018: Crossrail Ltd announces it will miss its December 2018 opening date but the central section “will open in autumn 2019”. The project is suffering from construction delays and difficulties installing complex signalling systems.
– December 2018: TfL says Crossrail may be delayed further and could require a £2 billion funding boost, taking the cost up to £17.6 billion. The Government, TfL and London Mayor Sadiq Khan agree on a financial package to cover this.
– December 2018: Sir Terry Morgan resigns as chairman of Crossrail Ltd and HS2, days after predicting he would be sacked. He is replaced at Crossrail by London Underground managing director Mark Wild.
– April 2019: A “delivery window” between October 2020 and March 2021 is announced for the central section of Crossrail.
– November 2019: Crossrail Ltd announces that the railway will open “as soon as practically possible in 2021”. The cost has increased by up to £650 million to £18.25 billion.
– January 2020: The “latest assessment” is that services will commence in summer 2021.
– July 2020: Crossrail Ltd says the railway will not open in summer 2021 because of delays caused by the coronavirus pandemic. It does not give an updated schedule.
– August 2020: It is announced that the line will open in the first half of 2022.
– July 2021: The National Audit Office says the estimated total cost of Crossrail is £18.9 billion.
– May 2022: TfL announces that the Elizabeth line will open in three separate sections on May 24. With the Queen visiting to announce the completion of the project.
– Autumn 2022: The lines from Reading, Heathrow and Shenfield are due to connect with the central tunnels.
– May 2023: The full timetable of up to 24 trains per hour is scheduled to be introduced.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel